管理番号20120000000282
タイトル*平成23年度中間年報 国際エネルギー消費効率化等技術・システム実証事業 省エネビル(ニューヨーク州立大学)実証事業(アメリカ)
公開日2012/5/10
報告書年度2011 - 2011
委託先名清水建設株式会社 Shimizu North America LLC
プロジェクト番号P93050
部署名省エネルギー部
和文要約和文要約等以下本編抜粋:
1. 研究開発の内容及び成果等について
平成23年9月30日に提出したFS成果報告書における適用技術提案に関し、来るべき実現化へのプロセスがスムーズにとり行われるよう、次の設計作業に注力した。
英文要約In developing the proposed schematic design as expressed in the feasibility study report dated September 30, 2011, work was focused on the following design works to ensure a smooth transition to the realization stage.
1) Items and the division of work for the technical applications of the FS Report were reviewed and adjusted for realization of the proposed systems under realistic conditions. Aspects such as scheduling, code requirements and/or standards, were considered in order to be ready for implementation discussions.
2) The UL standard, one of the key factors towards realization, has been studied carefully with the manufacturers and summarized into a chart.
3) The master schedule has been reviewed, taking into account lead times, installation and dry-run periods, to clarify when the design must be finished to authorize procurement and timely installation.
4) Based on the original specifications, the method and location of measurements for the interior environment was studied, and summarized into a test implementation plan.