成果報告書詳細
管理番号20130000000819
タイトル*平成23年度中間年報 米国ニューメキシコ州における日米スマートグリッド実証(15)
公開日2013/11/13
報告書年度2011 - 2011
委託先名伊藤忠商事株式会社
プロジェクト番号P09023
部署名スマートコミュニティ部
和文要約
英文要約Title: Japan-U.S. Smart Grid Collaborative Demonstration Project in the state of New Mexico/
Coordination of Collective Research, Operational Support to Demonstration Sites (FY2011-FY2012) FY2011 Annual Report

(1) Coordination of Collective Research:
・participating in and providing operational support to respective Collective
Research (CR1, CR5)meetings, facilitating and moderating meetings between
US researchers and collective research groups (CR1, CR5) as well as compiling 
meeting minutes
・providing support in the preparation of the May 31st “Collective Research
Workshop” (i.e. scheduling, conference room, agenda)
・providing support on standardization efforts (i.e. developing use case), including
facilitating in conducting the “Use Case Meetings” in Japan
・participating in JPRC meeting as a member and providing support in formulating
JPRC guidelines, as well as evaluation and discussion of research topics
recommended by US researchers
・providing operational support for meetings held by NEDO (i.e. preparation of
meeting materials and minutes)
・establishing preparatory Task Force to identify action items and scheduling
milestones for the Japan-U.S. Smart Grid Collaborative Demonstration Project
Workshop scheduled to take place in 2013

(2) Provide Operational Support to Demonstration Sites:
・participating in Site Meetings and providing support in addressing critical
issues as well as introducing viable solutions
・managing Delivery Task Force with Hitachi and providing support and advice for
delivering NEDO equipment to US sites
・arranging meetings on insurance issues and providing support for solving issues
including but not limited to “third party indemnification”
・providing support for identifying issues and collecting information on system
impact regulations from PNM and Sandia National Laboratory and sharing the information
with LAC site leader, TOSHIBA
・reviewing construction contract schemes and subsequent Implementation
Agreements with NEDO and Site Leaders
・participating in meetings with local engineering firms and providing advise on
critical engineering policy gaps between US and Japan
・proving support in creating good relationship with Los Alamos National
Laboratory to obtain irradiance data for PV output forecasting
・managing Smart Meter Task Force with NEDO and site leaders and addressing
critical issues as steps to formulate implementation strategy as well as drafting
scheduling milestones for Smart Meter Demand Response Demonstration