タイトル*平成24年度中間年報 インドネシア共和国・ジャワ島の工業団地におけるスマートコミュニティ実証事業
公開日2014/6/13
報告書年度2012 - 2012
委託先名住友商事株式会社 三菱電機株式会社 富士電機株式会社 NTTコミュニケーションズ株式会社
プロジェクト番号P93050
部署名スマートコミュニティ部
和文要約
英文要約1. Distribution automation system and Voltage stabilization system (Fuji Electric)
(1) Research requirements of Distribution automation system and Voltage stabilization system
In cooperation with PLN, we conducted a survey of requirements Distribution automation system and Voltage stabilization system in Indonesia.
-Field survey interviews sheet (completed)
-Benchmark report (30%, continued)
-Design proposal (85%, continued)

(2) Distribution automation system design 2
We designed of Distribution automation system in cooperation with PLN.
-Functional specification (30%, continued)
-Software design (50%, continued)

2. High-quality power supply system (Fuji Electric)
(1) study local plant
We proposed High-quality power supply system to factories and asked them to take part in the tryal project. We conducted field survey the target factories. in terms of location of receiving equipment.
-Selection of target factory (2 factories decided, continued)
-Field survey of the target factories (50%, continued)

(2) system design
WSe designed high-quality power supply system.
-20kV feeder equipment (80%, continued)
-High-quality power supply facilities (50%, continued)
-Factory's side facilities (50%, continued)

(3) Construction Plan
Based on the survey local factory, we planed the construction of the building electrical room high quality power supply system, the construction plan laying of transmission lines - electric room substation.
-Building high-quality power supply facilities (50%, continued)
-Factory's side facilities (30%, continued)

5. Cloud type FEMS (Fuji Electric)
(1) study factory
We proposed Cloud type FEMS to tenant factory and asked them to take part in the tryal project. We conducted field study the target factories.
-Selection of target factory(7 factries decided, ongoing)
-Field survey (50%, ongoing) of the target plant

(2) system design
Based on the requirements definition document, we have to design the system.
Basic functional specifications (60%, continued)
Evaluation report EMS integration (90%, continued)

6. Energy management system (Fuji Electric)
(1) study factory
We proposed Energy management system to tenant factory and asked them to take part in the tryal project. -We conducted field study the target factories.
-Selection of target plant (1 factory decided)
-Field survey of the target factory(continue)

(2) system design
Based on the requirements definition document, we have to design the system.
-Basic functional specifications (50%, continued)
-Planning function evaluation report (90%, continued)

7. Demand Side Manaegement System (Mitsubishi Electric)

8. Private FEMS (Mitsubishi Electric)

9. ICT platform(NTT Communications)
(1) Planing
We decided that the location of SCI network center was placed in the new building of high quality power supply facility. We confirmed the regulation and approval process for installing the fiber optic cables with SCI. We start negotiating the lines, which are between cloud platform and SCI, with local telecommunication carrier. We survey which data center we use for cloud platform system.
 
(2) System design
We designed telecommunication network infrastructure and chose each equipment specifically. We got the application requirement and confirmed specification.

(3) Construction schedule
We scheduled procurement and construction. The construction will be started at the third quarter FY2013. We will install the fiber optic cables in the each factory from April 2014.