タイトル*平成25年度中間年報 国際エネルギー消費効率化等技術・システム実証事業 基礎事業 石炭高効率利用システム案件等形成調査事業 褐炭改質技術、石炭灰利用技術、バイオマス利用技術の統合によるインドネシアの石炭低品位化対応ソリューション事業の案件発掘調査
公開日2014/12/27
報告書年度2013 - 2013
委託先名北陸電力株式会社 宇部興産株式会社 丸紅株式会社 一般財団法人石炭エネルギーセンター
プロジェクト番号P93050
部署名環境部
和文要約
英文要約Title: International Projects for Increasing the Efficient Use of Energy/ Project Formation Research on High-Efficiency Clean Coal Technology /The Investigation to Develop the Solution Business Coping with Low Rank Coal Produced in Indonesia by Optimal Integration of Technologies of Lignite Upgrading and Utilization of Fly-ash and Biomass.
Development item 1:
A study of upgrading low-rank coal plant installation
In the area of lignite upgrading, there are two investigation items;
1. Upgrading plant design.
2. Research for market and policy of upgrading business.
About #1, firstly we have received the EBL (Energi Batubara Lestari) coal sample (Hasnur asset) and conducted basic coal analysis as the reference of plant designing. And then, we visited the Hasnur assets of EBL coal mine, hauling road, jetty area, palm plantation, and palm oil refinery in order to collect the information and data for plant location and designing. Judging from these data and information collected from the visit and interview with Hasnur people, we have set plant site to be the vicinity of palm oil refinery. Plant capacity is determined to be 1 million ton of output per annum based on the research of Indonesian coal supply and demand prediction. By assembling above data and information, we have prepared the plant material balance, heat balance, process flow diagram, and equipment list.
About #2, we interviewed with a key person of ESDM (Energi dan Sumber Daya Mineral) to hear the government draft of lignite upgrading policy. Potentiality of application of this integration system and Indonesian coal supply and demand were investigated through the local consultant.
Development item 2:
The business potential of untapped natural resources and the system of their practical use
We examined the business potential of fly-ash soil conditioner and EFB (Empty Fruit Bunch) gasification power generation, and made the trial calculation of the greenhouse gas reduction effect by reducing consumption of the fossil fuel accompanying the use of EFB.
We manufactured fly-ash soil conditioner, and offered it to the experiments in Indonesia.
We performed pH measurement and specimen extraction of acid soil at the coal mine in Indonesia, and started the experiments to verify the application effect of fly-ash soil conditioner as well as the durability of its soil improvement effect.
We implemented the conceptual design and cost estimate of building the plant and equipment to manufacture fly-ash soil conditioner in Indonesia.
We conducted market research of the existing soil conditioners and fertilizers which could possibly compete against our fly-ash soil conditioner in Indonesia.
We conducted investigation of infrastructure to transport fly-ash soil conditioner in Indonesia.
We conducted investigation of the regulation about use of fly-ash soil conditioner.
We examined the amount of EFB generated in the plantation at mining company.
We examined EFB gasification-power-generation equipment.
Development item 3:
Business assessment and business problem extraction
After integrating 3 plants (Lignite Upgrading, Soil Conditioner, EFB Gasification), we have estimated CAPEX, OPEX, IRR, and CO2 reduction in base case of integrated plant operation.