管理番号20150000000483
タイトル*平成26年度中間年報 国際エネルギー消費効率化等技術・システム事業 フランス・リヨン再開発地域におけるスマートコミュニティ実証事業
公開日2015/6/25
報告書年度2014 - 2014
委託先名東芝ソリューション株式会社 株式会社東芝
プロジェクト番号P93050
部署名スマートコミュニティ部
和文要約
英文要約Title:Lyon Smart Community Demonstration Project (FY2011-FY2015) FY2014 Annual Report

1.Content and Achievements of the Demonstration Project
Task1: Major pieces of equipment from the Japanese side were delivered for the PEB development of the Hikari (P-Plot) Building, which will start operations by the first half of 2015.
Task2: Phase 1 and 2 of operations began in October 2013 and July 2016, respectively, for the EV Car Sharing System powered by renewable energy.
Task3: Energy Management Systems for use in existing homes started operations in November 2014.
Task4: CMS, which aims to make energy-related real-time information available to public administrators, started data collection in November 2014.

(1)Task1: Positive Energy Building (PEB) Development of the P-Plot Building [Toshiba]
a)Commissioning
A procedure manual to be used during the test adjustment stage for Principal Commissioning (P-Cx) was drafted. Based on this manual, plans for equipment verification tests and environmental measurement were made, which the French side agreed with.
b)Local Equipment
Specifications for the equipment coming from the Japan side were discussed and decided through discussions with Bouygues Immobilier, MANASLU, and SETEC. The said equipment has already been delivered to the site.
c)System Equipment (BEMS and HEMS)
Functional specifications of BEMS and HEMS were made based on the BEMS/HEMS specifications that were decided from discussions with Bouygues Immobilier, MANASLU, COFELY AXIMA, and SNEF. The delivery of sensors and cabinets has already been started.
(2)Task2: EV Car Sharing System Powered by Renewable Energy [Toshiba Corporation, Toshiba Solutions Corporation]
a)Schedule Optimization System
Phase 2 of the Schedule Optimization System has been developed and has started operations. The system calculates EV charging time using estimated PV generation and car sharing reservation data to maximize the use of the PV-generated power.
b)μEMS
An μEMS function that estimates PV generation based on weather forecasts from Meteo France and actual PV generation data has been developed and completed testing. The said function has already been incorporated in operations.
c)Start of EV Car Sharing (Phase-2) Operations
The operation of Phase 2 of the EV Car Sharing System has started from July 1, 2014.
(3)Task3: Energy Management Systems for Existing Homes [Toshiba Corporation, Toshiba Solutions Corporation]
a)Energy Visualization
An energy visualization system that provides information on electricity, gas, and water consumption and offers tips for energy savings has been developed. It has already started operations.
b)Installation Work
The installation and configuration of multi-circuit power recorders and add-on devices in participant households in Cite de Perrache has been completed.
(4)Task4: Community Management System (CMS) [Toshiba Corporation, Toshiba Solutions Corporation]
a)Start of data acquisition
The collection of data from Task 2 and Task 3 began in June 2014.
b)Connection to other buildings
The K-Plot (medium-size, mixed-use type) and C5 (small office type) buildings located in the Lyon Confluence will be connected to the CMS. Details on the data to be collected and the communication interface have already been decided.