成果報告書詳細
管理番号20150000000484
タイトル*平成26年度中間年報 インドネシア共和国・ジャワ島の工業団地におけるスマートコミュニティ実証事業(1)
公開日2015/8/13
報告書年度2014 - 2014
委託先名住友商事株式会社
プロジェクト番号P93050
部署名スマートコミュニティ部
和文要約
英文要約Summary of Interim Report for FY2014

1. Installation and commissioning of high quality power supply system
(1) Installation
-1) Supply and construction of building for high quality power supply system
Civil construction and building construction based on the design drawings has been done. However, the building construction has not been completed and it will be continued. Expected complete date is end of April. (80%, ongoing)

-2) Equipment (UPS, Battery) installation
Equipment installation has not been done due to the delay of equipment delivery.

-3) Cable installation between the building and factories
Cable installation for high quality power between the building and factories has been done. (80%, ongoing)

-4) Distribution panel installation
Equipment installation has not been done due to the delay of equipment delivery.

2. Planning of installation and commissioning
-1) Planning of installation
Planning of civil, construction related to the building construction has been done. For other equipment installation will be done after the equipment delivery has been fixed. (50%, ongoing)
-2) Planning of commissioning
Planning of commissioning has not been done due to the delay of equipment delivery.

3. Insurance
-1) Insurance
Insurance arrangement for building construction has been done. Insurance for equipment installation will be done after the equipment delivery has been fixed. (50%, ongoing)

4. Land lease
-1) Agreement for the Land
The condition of the land usage has been discussed with SCI. The agreement was made and signed by SCI. (100%, completed)

-2) Maintenance of building
Since we started the construction work, the maintenance work related to the land and building has been done. (20%, ongoing)