タイトル*平成26年度中間年報 太陽光発電多用途化実証プロジェクト 太陽光発電多用途化実証事業 傾斜地用太陽光発電システムの実証(H25-H27) 
公開日2016/4/22
報告書年度2014 - 2014
委託先名株式会社アドテック富士
プロジェクト番号P13008
部署名新エネルギー部
和文要約
英文要約Title: Development and Demonstration of Technology for More Versatile Application of Solar Power / Demonstration of the solar power generation system for slope lands (FY2013-2015) FY2014 Annual Report

4. Development and evaluation of automatic construction equipment. The automatic construction equipment which can install a solar cell onto its supporting structure automatically safely and easily is developed. (1)Evaluate about working efficiency and safety of a panel supply process. Compare 5 kinds of manual mini model with 2 kinds of automatic mini model,estimate and inspect them. Then evaluate about working efficiency and safety of a panel supply process, devised a basic structure of Automatic Installation Equipment and investigated its basic specification. (2)Make a detailed design for automatic installation equipment. The basic specification was decided about based on the basic structure contrived by a stand (Adjustable stand) for slope land and a mini model. The trial automatic installation equipment shall consist of two parts;an installation machine (Fig.-1) and a carry machine (Fig.-2). The installation machine is the one which can install a solar panel onto the stand and the carry machine is the one which carry the solar panels.(3)Manufacture the trial automatic installation machine. The trial automatic installation machine was built and be adjusted.It was operated in the laboratory and the panel was installed actually.(4)Evaluation for the automatic working efficiency at the actual site. Setting the solar panel onto the stand (Adjustable stand) for slope lands at the actual site, Working hours, working efficiency, the worker necessary number of people, safety, details of work and a working place for operator were estimated, then we confirmed that the working hours could be reduced.
5. Modelling of system installation. To establish the installation model for commercialization with municipalities and private companies that own unused lands, and conduct promotional activities. (1)The generating electricity cost of the solar power generating system for slope lands was calculated as a test.

Working hours, working efficiency, the worker necessary
number of people, safety, details of work and a working place for operator
were estimated, then we confirmed that the working hours could be reduced.