成果報告書詳細
管理番号20160000000415
タイトル*平成27年度中間年報 インドネシア共和国・ジャワ島の工業団地におけるスマートコミュニティ実証事業(2)
公開日2016/6/24
報告書年度2015 - 2015
委託先名住商機電貿易株式会社 三菱電機株式会社 富士電機株式会社 エヌ・ティ・ティ・コミュニケーションズ株式会社
プロジェクト番号P93050
部署名スマートコミュニティ部
和文要約
英文要約Summary of Interim Report for FY2015
1. Distribution automation system and Voltage stabilization system (Fuji Electric)
(1) Field survey of Voltage stabilization system: (0%, not started due to the suspension of the project)
2. High-quality power supply system (Fuji Electric)
(1) Field survey of factories: (95%, ongoing)
(2) System design
-Factory's side facilities (100%, completed)
(3) Manufacturing
-Factory side facilities (0%, just ordered)
3. Demand Side Management System (Mitsubishi Electric)
(1) Requirements research for DSM system
-Definition of DSM system requirement (100%, completed)
(2) Investigation of local factories
- Proposal of participating in DSM trial (acceptance: 22 factories, interrupted)
(3) System Designing
- System Design (100%, completed)
(4) System Development
- DSM Software Designing (100%, completed)
- Energy measurement tool (100%, completed)
- Preparation of equipment shipment (20%, ongoing)
4. Private FEMS (Mitsubishi Electric)
(1) Investigation of local factories: (1st investigation 100% completed, 2nd investigation 0%)
(2) System designing: (100%, completed)
(3) System development(-FEMS Manager Equipment and software):(95%,ongoing)
(4) Equipments installation into factories (20%, ongoing)
5. Cloud type FEMS (Fuji Electric)
(1) System development: (100%, completed)
-Transition plan to the cloud system
-Study of site test items
-Study of the analysis item of the collected data
6. Energy management system (Fuji Electric)
(1) System development
-System test in Japan (0%, not started due to the suspension of the project)
7. ICT platform(NTT Communications)
(1) Field survey: (100% completed)
(2) Planning
-1) Location of network center in SCI: (100% completed)
-2) Location of fiber cable installation: (80%, ongoing)
-3) Transmissions: (100%, completed)
-4) Location of data center: (100%, completed)
(3) System design
-1) Design of telecommunication infrastructure: (90%, ongoing)
-2) Design of cloud platform: (90%, ongoing)
8. Common (Sumisho Machinery Trade Corporation)
(1) Investigation of foreign investment
-1) Indonesian government has released new negative list on 11 Feb, 2016. The new list is increased the maximum rate of foreign investment on 64 industries. Also, foreign investment is newly released for 20 industries which were allowed only for Indonesian investor.
(2) Regulation issues
-1) High Quality Power Supply System
Tariff of electricity has been specified by the regulation from Ministry of Energy and Mineral Resources and the tariff for HQPS shall be categorized as a Special Service in the regulation. The tariff of special service is IDR1,650/kWh however the maximum rate is IDR2,475/kWh including multiplier factor. Also, the implementation of tariff shall be determined by the board of directors of PLN.
-2) DSM incentive
PLN has an experience to perform the DSM program as a trial service but there is no regulation for commercial use of DSM program. Therefore, new regulations for DSM program are required to perform as the commercial services.