成果報告書詳細
管理番号20090000000083
タイトル*平成20年度中間年報 バイオマスエネルギー地域システム化実験事業 高知県仁淀川流域エネルギー自給システムの構築
公開日2009/7/30
報告書年度2008 - 2008
委託先名高知県吾川郡仁淀川町
プロジェクト番号P05004
部署名新エネルギー技術開発部 バイオマスグループ
和文要約以下本編抜粋:1.研究開発の内容及び成果等 1-1大規模林産現場(架線集材)におけるバイオマス収集 (1)運搬コストを削減するために運搬用トラックの大型化の検討を行った。主な成果は以下のとおり。大型ダンプは荷台が高くそのままでは荷台内が見えないので整理しながら積載できないことから積載量が少ない。荷台をカメラ等を利用し可視化して積載量を多くする方法を考え実験を行った。
英文要約Development Item “Biomass Energy Regional Systematization Experiment Project/Configuration of Kochi Prefecture Niyodo River Basin Energy Self-Supply System”
Interim Annual Report 2008 in 2007 through 2009
Prepared by (consigned to): Niyodogawa-Cho, Kochi Prefecture
1.Description and Achievements of Research & Development
1-1 Biomass Collection at Large-Scale Forest Product Sites (collection by cable yarding)
(1)In order to reduce transportation cost, how larger sizes of trucks could be used for transportation was studied.
(2)Periodical costs were identified.
1-2 Biomass Collection at Medium-Scale Forest Product Sites (material collection by vehicle-series forest machines)
(1)Efforts were made to reduce expenses in collection and transportation (improve collection efficiencies).
(2)Periodical costs were identified.
1-3 Biomass Collection at Small-Scale Forest Product Sites (collecting materials by NPO and individual forestry family)
(1)In the small-scale collection, a quantitative examination and a study to stabilize the amounts of collection were conducted.
1-4 Making Biomass Chips
(1)Trade by water content was implemented as an incentive to encourage better biomass (biomass with less water content) to be brought to us.
(2)How to store pre-chipping biomass was examined.
(3)Periodical costs were identified.
(4)In order to deal with anything that cannot be solved by existing crusher, how new-type crusher can be introduced was studied.
1-5 Collection, Analysis and Examination of Operation and Its Data of Energy Conversion/Utilization Systems
(1)Operation of energy conversion system
Demonstration test was conducted with the energy conversion system consisted of gasification power generating system and pellet manufacturing system, and the basic performance, maintainability, safety and running cost of the energy conversion system were identified, so that improvement might be made. Main results are as shown below.
(2)Collection, analysis and examination of data of operation and economy of energy conversion system
Data of the operation and economy of energy conversion system were collected, analyzed and examined, so that improvements might be made. Main results are as shown below.
(3)Acquisition, analysis and examination of operation data of systems using pellets
(4)In order to improve energy efficiencies and effectively utilize sub-products, charcoal pelletization system was introduced.