成果報告書詳細
管理番号20110000000613
タイトル*平成22年度中間年報 「国際エネルギー使用合理化等対策事業 国際エネルギー消費効率化等モデル事業 民生(ビル)省エネモデル事業(タイ)」
公開日2011/5/10
報告書年度2010 - 2010
委託先名中国電力株式会社
プロジェクト番号P93050
部署名エネルギー対策推進部
和文要約和文要約等以下本編抜粋:(1) 実証事業の内容
(事業概要)
バンコクの中心部に位置するアマリ・ウォーターゲートホテルに対して、高効率機器の導入、インバータを活用した搬送動力削減などの省エネルギー技術およびBEMS
(Building Energy Management System)によるエネルギー管理・運用の最適化など我が国の省エネルギー技術を複合的に組合せて導入し、その有効性を実証する。さらに、モデルプラントの実証運転、普及セミナー等を通じて、本技術のタイ国内への普及を推進する。
英文要約Title: Model Project for Reducing Energy Consumption in a Commercial Building in Thailand (FY2010-FY2012) FY2010 Annual Report : Adopting combined Japanese energy conservation technologies, which are high-efficiency equipment, energy conservation of transportation power by using inverter and optimization of energy management and operation with BEMS (Building Energy Management System), to Amari Watergate Hotel located in the central of Bangkok, effectiveness of technologies shall be demonstrated. Furthermore, the technologies shall be promoted in order to disseminate it in Thailand by the demonstration, dissemination seminar and so on. : (1) Site survey: Draft ID was prepared with the results of following site survey that was essential to make up the basic plan for ID > Detailed survey including the site condition or Thai standard etc. - Research of Thai standard - Measuring room temperature and water survey of tap water - Verifying the layout of existing electrical and mechanical facilities > Study of the basic plan such as construction technique for installing equipment and verification method of effectiveness - Site survey regarding the transportation method such as hoisting the large-size equipment with crane etc. - Checking the current condition of the existing facilities that might affect installation work - Clarification of the impact to Amari Watergate Hotel’s operation during construction (Usage restriction of air conditioning facilities, occupation for work space and passageway etc.) - Study of the method to verify the effectiveness of energy conservation technologies (2) Agreement related services: Discussion with Amari Watergate Hotel regarding Implementation Document (ID) is ongoing. Assistance work for Minute of Understanding (MOU) between NEDO and Ministry of Energy in Thailand is ongoing
ダウンロード成果報告書データベース(ユーザ登録必須)から、ダウンロードしてください。

▲トップに戻る