タイトル*平成29年度中間年報 エネルギー消費の効率化等に資する我が国技術の国際実証事業/圧縮天然ガス (CNG)車普及に向けたインフラ構築を含む持続可能な環境整備・実証事業(インドネシア)
公開日2018/6/26
報告書年度2017 - 2017
委託先名トヨタ自動車株式会社 日野自動車株式会社 豊田通商株式会社 東邦ガスエンジニアリング株式会社 一般財団法人日本自動車研究所
プロジェクト番号P93050
部署名省エネルギー部
和文要約
英文要約Title: Demonstration Project for the Spread of Compressed Natural Gas Vehicles and Refueling Infrastructure including Support of Development of Sustainable Environment in Indonesia (FY2017-FY2020) FY2017 Annual Report

1. Two Implementation Documents on construction and operating of CNG stations were contracted with Pertamina on January 22, 2018.

2. Demonstration related work
1) A vehicle lease basic contract was made at the end of March.

2) CNG passenger cars
The schedule of providing 10 cars is as follows, production in Thailand in June 2018, export and import between July and August, and certification between September and November.
Users’ monitor will start in January 2019 for two years as follows;
At the 1st stage: MIGAS and other sections under ESDM 5, DEN 1, Pertamina 3 and a Toyota Indonesia 1
At the 2nd stage: Japanese local corporations 6, Pertamina 3 and a Toyota Indonesia 1

3) CNG trucks
The schedule of providing 18 vehicles is as follows, production in Thailand in April 2018, export and import between May and June, certification between July and September, and bodywork between October and December.
Users’ monitor will start in April 2019 for two years as follows;
Use of a Mobile Refueling Unit until running of a new refueling station at Karawang is being adjusted with Pertamina.
Users will be total 11 shipping companies, for milk run of auto-parts 5, periodic delivery of auto-parts 2, general materials 3 and fuel delivery 1.

4) Local adjustment of refueling stations concerning design and construction
Layout and power specification of 2 city-type refueling stations at Abdul Muis and Sudirman Tangerang are confirmed with Pertamina.
A work schedule and specification of 1 industrial estate-type refueling station at Karawang are shared with an industrial estate management company.

5) CNG market trend
A state of the CNG refilling stations is surveyed for making a refueling station map (21 in operation).
Due to the free distribution of CNG converter kits by the government, many CNG taxis are refilling up, e.g. 600 taxi per day at Mampang station by interview.
In Jakarta, new gasoline “Pertalite 90” (7600 Rp /L) is popular, and the price difference with CNG (3,100 Rp/L) expands. It is expected to spread CNG cars.

3. Making a basic plan
1) Driving monitor plan of CNG vehicles: Same as 2-2) and 2-3)

2) Construction and operating monitor plan of the CNG refueling stations
The schedule will be as follows, factory inspection in Japan by MIGAS in January 2019, export, import and installation between June and July, start of running in December after certification and commissioning, and monitoring for 1 year and 4 months.

3) A plan of analyzing CNG fuel quality
Gas sampling and quality analysis will be implemented for demonstration refueling stations and existing ones between FY2018 and FY2020.

4. Basic agreement with Pertamina on system, main equipment configuration and layout of each refueling station is completed.

5. Ordering of major station equipment starts sequentially.