本文へジャンプ

成果報告書詳細
管理番号20190000000231
タイトル*平成30年度中間年報 国際エネルギー消費効率化等技術・システム実証事業/ウズベキスタン共和国における分散型中・小型ガスタービン高効率コージェネレーションシステム実証事業
公開日2019/5/14
報告書年度2018 - 2018
委託先名丸紅ユティリティ・サービス株式会社 川崎重工業株式会社
プロジェクト番号P93050
部署名省エネルギー部
和文要約
英文要約Title: Technical and System Demonstration Projects for Increasing the Efficient Use of Energy,
International Demonstration Projects for high efficiency co-generation system by distributed middle-small sized gas turbine in the Republic of Uzbekistan (FY 2016 - FY 2020) FY 2018 Annual Report
Summary of the results in FY 2018
(1) RK-3 site (7MW gas turbine co-generation)
・Dispatched technical advisor(s) and explained carry-in and installation procedure of 7MW gas turbine co-generation in May 2018.
・Shipped out 7MW gas turbine co-generation equipment from Kobe, Jakarta and Singapore throughout the months of June until July 2018 and delivered to Uzbekistan. Dispatched technical advisor(s) throughout the months of September until December 2018 and completed carry-in and installation of Japanese side main equipment.
・Dispatched technical advisor(s) to give advice on temporally storage for Japanese side equipment in November 2018.
(2) Fergana CHP site (17MW gas turbine co-generation)
・Held design conference on electric and control equipment in October-November 2018 and completed production of Japanese main equipment after design and engineering work for 17MW gas turbine co-generation is completed.
RK-3 and Fergana CHP site
・Gave advice on overall schedule control and design & procurement schedule.
・Dispatched technical advisor(s) to give advice on civil construction, mechanical, electrical, utility and control system etc.
・Arranged translation of design and manual documents into Russian and provided Uzbekistan side.