管理番号20190000000401
タイトル*平成30年度中間年報 「エネルギー消費の効率化等に資する我が国技術の国際実証事業/圧縮天然ガス(CNG)車普及に向けたインフラ構築を含む持続可能な環境整備・実証事業(インドネシア)」
公開日2019/5/22
報告書年度2018 - 2018
委託先名トヨタ自動車株式会社 日野自動車株式会社 豊田通商株式会社 東邦ガスエンジニアリング株式会社 一般財団法人日本自動車研究所
プロジェクト番号P93050
部署名省エネルギー部
和文要約
英文要約Title: Demonstration Project for the Spread of Compressed Natural Gas Vehicles and Refueling Infrastructure including Support of Development of Sustainable Environment in Indonesia (FY2017-FY2020) FY2018 Annual Report

1. Project management
- The kickoff meeting (July 19) and the first progress meeting (October 4) were held in Jakarta to share issues, cooperation items, and the direction of institutional design support.

2. Demonstration related work
1) Contract concerning CNG vehicle monitoring
- A leasing company and 3 consortiums signed contracts among users, though only a basic contract was signed about trucks.
2) Delivery of CNG passenger cars
- Vehicle certification was acquired and 10 cars was delivered in March. Users are MIGAS, Pertamina and TMMIN, etc.
3) Delivery of CNG trucks
- Vehicle certification was acquired and 18 trucks will be delivered to 9 logistics companies after May.
4) Local adjustment of SPBG concerning design and construction
- Specifications of SPBGs were agreed with Pertamina and Pertamina Gas. The basic design of the Japan-side work scope was completed.
- For the SPBG at Karawang, the detailed design and preparation work were carried out with the local construction company.
5) CNG market trends
- SPBGs map on the Google Map was made for the vehicle monitoring users and extension policy studies.
6) Institutional design support
- There are three points through the above activities.
a) Written examination is considered sufficient for CNG cylinders certified by UNECE.
b) A mechanism is needed to quickly procure replacement parts for SPBG equipment recovery.
c) A steady maintenance system is necessary due to gas leak of taxi and loosening of small bus filling port.

3. Basic and detailed design (SPBG)
- Basic design of 3 SPBGs were completed based on each equipment makers' design, and also detailed design at Karawang was completed.

4. Equipment procurement, production, transportation and insurance (SPBG)
- For compressor, dryer, storage, and control panel, MIGAS and inspection agent visited the factories in Japan for inspection, and all passed. Equipment has been shipped to bonded warehouse in the Kobe port, waiting for export.

5. Site construction work (SPBG)
- A main bridge is under construction at Karawang. Japanese side is waiting for working visa application.

6. Trial operation and demonstration (vehicle)
- Data communication confirmation of 10 passenger cars has been completed, and a hand-over meeting was held with users on March 28. The monitoring has started.
- Driving test with a truck on the highway between Cikampek and Bandung was done. The ability to climb the hill when fully loaded is practically acceptable. The data communication of digital tachometer will be confirmed in April after obtaining permission for communication authentication.

7. Results of presentation
- Presented on the project outline and progress at the Japan-Indonesia Energy Forum (May 8).
- Exhibited a demonstration CNG truck at the Jakarta Motor Show (August 2-11).